Strategic Risk Register – October 2026

This Register details the strategic risks faced by Mole Valley District Council in relation to achieving the priority outcomes and guiding principles as defined in the Council Strategy. It also notes the controls in place to mitigate the risk. These controls do not constitute MVDC internal procedures and may be amended to reflect the assessed risk level. The Register is owned by the Chief Executive.

Corporate Priorities

  • Fairer – Supporting individuals and communities to lead safe, healthy and fulfilling lives.
  • Greener – Striving to become carbon neutral and maximising opportunities to ensure Mole Valley remains a highly attractive area.
  • Opportunity – Enabling a prosperous local economy with thriving towns and villages.
  • Progressing Together – Working with our partners and the Mole Valley community, our mission is to transform our services to ensure that they are modern, valued, efficient, digital by choice and accessible by all.

 

Code and TitleProbabilityImpactRisk Score
C1 Financial Sustainability133
C1d Reduction in capital value of and rental income from investment properties236
C3 Corporate Health and Safety248
C4b IT systems – b) Risk of hacking236
C5 Data Protection / Information Governance224
C7 Organisational capacity to deliver248
C8 Safeguarding224
C9 Climate change3412
C11 Asset Redevelopment and Regeneration2510
C12 Emergency planning236
C13 Contract management326
C14 Waste services248
C15 Local Government Reorganisation236
C16 Exceeding VAT partial exemption limit236

Controls in place
These are some of the key activities that officers undertake to mitigate the risk. They do not constitute MVDC internal procedures and may be amended to reflect the assessed risk level.

There is a risk, due to the national economic climate, action taken in response to Local Government Reorganisation and the recent review of local government finance, that the Council is unable to balance its budget, without impacting significantly on service delivery and performance. The pressures that MVDC face are to a large extent shared by our contractors and neighbouring councils. This is in the context of a medium term future which may well include:

– A loss of government funding as a result of a review of local government finance (Fair funding review and Business rates retention reset).  The fair funding review outcome was announced in December 2025, for 2026/27 MVDC has an overall increase in Settlement Funding Assessment (SFA) of 3.47% as a result of transitional arrangements, however this will reduce by 4% in 2027/28 and a further 4% in 2028/29.

-Business rates income being below the Business Rates Baseline assessed by Government, meaning that the Council falls into the Business rates ‘Safety Net’.  This means that the Council is not collecting as much Business Rate income as the Government has assessed it should be able to collect and as a result the Council will loose income.  The Council can only reclaim 100% of the lost income in 2026/27 as a result of the Safety Net being set at 100%, for 2027/28 the Safety Net will be 97.5% and in 2028/29 and beyond it will be 92.5%.

-The re-organisation of councils in Surrey into two new Unitary Councils, MVDC needs to fund £539,000 of implementation costs associated with the reorganisation prior to vesting day.  The post-vesting day implementation costs of around £27million will need to be funded by the New East Surrey Council.

– Material costs of refurbishment of some Council assets

– Re-tendering/mobilisation of a number of Council services which were last re-let when market conditions were very favourable to the Council

-Additional costs of recycling processing as a result of a recent fire at the Council’s Material Recycling Facility (MRF) at Randalls Road

– Rising demand for services, such as homelessness

Please also see Risk C11 on Asset Redevelopment and Regeneration and Risk C14 on Waste Services

Inherent risk level (no controls)

Probability: 4

Impact: 5

Risk score: 20 (red)

Controls in place at MVDC

– Maintaining robust budget monitoring and, if appropriate, corrective action to ensure spending is in line with the Budget

– Robust re-procurement procedures

– Contract management arrangements in place and IA actions being addressed (see separate risk)

– Transformation savings plan in place, with proactive monitoring and reporting of savings realisation to the Strategic Leadership Team and as part of the regular Business and Budget monitoring reports to Cabinet

– Transformation programme developed for 2026/27 identified £504,000 of savings to help balance the 2026/27 budget, monitoring of the programme to date shows that the Council is on track to achieve the savings.

– Financial Strategy and Medium Term Financial Plan in place

Residual risk level (after existing controls)

Probability: 1

Impact: 3

Risk score: 3 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 1

Impact: 3

Risk score: 3 (green)

Risk owner – Member

Cabinet Member (Finance)

Risk owner – Officer

EHoS – Resources

Rents from our investment property portfolio are a key source of income and the capital value of the property is a significant asset on the Council’s balance sheet. This risk is informed by a number of factors including the national economic climate; uncertainty in the property and financial markets; recent government budget changes (e.g., to national insurance); potential reform (or lack of reform) of business rates; material changes in the way of doing business such as online shopping and hybrid working.

Factors that can increase the risk are:

  • Loss of rent and reduction of income to MVDC (e.g. tenants struggling to pay their rent; tenants not renewing their leases or exiting leases early, tenants opting to exercise lease breaks in order to downsize, leading to a rise in empty/partially empty premises and void periods; the need to provide incentives to attract new tenants)
  • Inability to maximise income to the Council through reviewing rents at appropriate rent review dates within leases (including those with ‘time is of the essence’ clauses)
  • A reduction in the capital value of the assets on the council’s balance sheet, and (for assets funded by borrowing), the value of the asset no longer being sufficient to repay the remaining debt, resulting in a potential overhanging MRP charge to the Council’s revenue account in the event of a disposal
  • Inability of MVDC’s commercial assets to achieve an Energy Performance Certificate B rating by 2030 (as stated by the previous government). Without that rating it may difficult or impossible to let previously tenanted properties.

Inherent risk level (no controls)

Probability: 4

Impact: 4

Risk score: 16 (red)

Controls in place at MVDC

-Asset Management Strategy approved by Cabinet in June 2025 and being implemented

– Proactive, rational and flexible approach to rent negotiations (rent reviews) and service charge liability

– Proactively seeking new lettings and maximising income from existing assets, or pursuing change of use / disposal strategy

– Good understanding of the local property market and national movement across all sectors

– Positive relationship with tenants and Swan Centre Managing Agents

– Asset Managers confirm that demands have been received 2 weeks prior to the quarter day, then chasing payment after the quarter day on a weekly basis as a minimum, referring to legal at week 4 if the payment is still outstanding

– Performance management of rental income reported to Cabinet in Business and Budget monitoring reports

– Proactive engagement with tenants identified to be at risk (factors include covenant deterioration, payment history and business sector)

– Regular monitoring of aged debt to identify any pattern in non-payment

– Payment plans put in place for tenants who are in arrears

– Proactively seeking rent deposits and/or guarantors where possible for new lettings

– Monitoring of tenant covenant strength in relation to AIS properties and annual review of investment assets for market intelligence to manage associated risk

– Asset Managers maintain EPC records for commercial buildings and, where poor energy performance is likely to impact lettings under MEES, produce property specific management plans identifying actions required to address

– Regular reporting of asset management dashboard to corporate governance board to provide oversight of property portfolio and ensure balance of risk regarding current and future rental income

-Use of property advisors to provide guidance on hold strategy

-Actions from previous Internal audit and CIPFA review of asset management fully implemented and reported

-Asset reviews reported to strategic asset management working group

-Implementation of 31Ten and Arlingclose recommendations to restructure MOVA balance sheet and loan agreement

Residual risk level (after existing controls)

Probability: 2

Impact: 3

Risk score: 6 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 2

Impact: 3

Risk score: 6 (green)

Risk owner – Member

Cabinet Member (Commercial Assets and Projects)

Risk owner – Officer

EHoS – Resources

MVDC needs to provide services in a safe manner that protects the health and safety not just of its employees but also members of the public, trainees, contractors, Members and those who undertake work on behalf of MVDC. If we fail to have good Health and Safety arrangements in place, this could lead to loss of service and / or preventable accidents to and ill health of staff, contractors, public or others affected by our undertakings. This is of particular importance due to the nature of some of the services we provide to the public and vulnerable people.

This risk is informed by:

  • Compliance with Health and Safety at Work Act
  • Public duty
  • Any other legislation that seeks to prevent accidents, ill health and injury

Inherent risk level (no controls)

Probability: 5

Impact: 5

Risk score: 25 (red)

Controls in place at MVDC

– Corporate Health and Safety Policy, arrangements and procedures in place and regularly reviewed / audited

– Regular spot check reviews of health and safety arrangements by Health and Safety consultant

– Regular meetings of H&S Group, who escalate any concerns to Corporate Governance Board

-Health and Safety Group briefed on upcoming and amended Health and Safety legislation

– Health and Safety action plan in place

– Employee induction includes focus on Health and Safety and all employees provided with Health and Safety Guidance

– Training in place for new and existing employees with specialist training provided as required

-Organisational stress risk assessment in place and reviewed annually

– Health and Safety risk assessments in place for all service areas and regularly reviewed

– Lone working procedure in place for all service areas with bespoke arrangements in relation to individual business areas

– Effective management/inspection of property and land assets

– Health and safety integrated into procurement processes and contract management processes

– Arrangements with partner organisations/ below procurement threshold contracts to ensure appropriate Health and Safety requirements are in place

Residual risk level (after existing controls)

Probability: 2

Impact: 4

Risk score: 8 (amber)

Movement of residual risk since last review

None

Target risk level

Probability: 2

Impact: 4

Risk score: 8 (amber)

Risk owner – Member

Leader, Governance and Organisation

Risk owner – Officer

Deputy Chief Executive

MVDC typically blocks thousands of malicious attempts daily to access MVDC systems and data. The majority are blocked by technical measures. The most significant contributor to this risk is that MVDC employees and members may, for example, inadvertently click on malicious links or attachments in Phishing emails.

If we fail to secure the Council’s accounts and data there is a risk of loss and data protection issues; this could lead to the Council not being able to deliver services, financial cost of rebuilding and ICO fines, and reputational damage.

Inherent risk level (no controls)

Probability: 5

Impact: 5

Risk score: 25 (red)

Controls in place at MVDC

– ICT Security Policy in place and regularly updated

– Access to systems and data is strictly controlled and data is held securely in order to ensure it is only available as permitted and not at risk of loss or compromise

– Regular testing of the ICT security perimeter (firewalls), monitoring for new vulnerabilities of systems and a cycle of ensuring all system versions are up to date is in place. Quarterly review, and if required housekeeping, of Firewall rules

– Regular patching cycle of server and desktop infrastructure, and also monthly review of security systems (Proxy server, firewalls, switches, backup software, HCI software)

– Risk assessment on basis of industry knowledge and government information provided by the National Cyber Security Centre

– Regular mandatory Cyber security awareness training for all Council Officers. Extended on a voluntary basis to Councillors

-Regular awareness and communications for staff on intranet

Residual risk level (after existing controls)

Probability: 2

Impact: 3

Risk score: 6 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 2

Impact: 2

Risk score: 4 (green)

Risk owner – Member

Cabinet Member (Services and Security)

Risk owner – Officer

EHoS – People

MVDC needs to make sure that personal data is secure and only processed in accordance with the relevant legislation and that an individual’s right to privacy and other access rights are protected, including consideration and monitoring in preparation for Local Government Reorganisation.

If we fail to effectively act on and embed standards and procedures that enable us to do this, this could lead to distress and harm for data subjects, a loss of public trust, financial penalties to the organisation, or other regulatory action as imposed by the Information Commissioner’s Office

This risk is informed by a number of issues, including:

  • Potential data protection breaches, misuse of private information, breaches of European Convention of Human Rights (Article 8) and breaches of confidence enabling access to confidential data
  • Loss of data, including as a result of malicious cyber security attacks (Ref:C4b, Risk of Hacking)

Inherent risk level (no controls)

Probability: 5

Impact: 5

Risk score: 25 (red)

Controls in place at MVDC

– Data Protection Policy approved by Council and updated periodically

– Data protection training and updates for new and existing staff

– Member Training on responsibilities under appropriate Code of Conduct, including data protection, for new and existing Members, and training video on MOSS

– Certification obtained on disposal of confidential information

– Information Asset Register in place for each service

– Records Retention Policy and schedule in place and implemented

– Data sharing protocols in place and implemented

– Data protection procedures in place to for all new projects and processes

– New software systems functionality and use evaluated for GDPR compliance

– Procedures in place for compliant use of email by staff/Members and document management arrangements

– Procedures in place to ensure that personal information is not inadvertently made available in the public domain

-Participation in the Information Governance workstream (and monitoring any changes to associated processing) within the LGR Implementation Programme

– Statutory Data Protection Officer (and Deputy) in place

– GDPR guidance in place to reflect move to hybrid working

– Data security threats (e.g through phishing) addressed in C4b (risk of hacking) controls

Residual risk level (after existing controls)

Probability: 2

Impact: 2

Risk score: 4 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 2

Impact: 2

Risk score: 2 (green)

Risk owner – Member

Cabinet Member (Commercial Assets and Projects)

Risk owner – Officer

EHoS – Commercial

If we fail to ensure that the organisation continues to have the capacity to achieve the priorities in the Annual Plan, and ensure the effective delivery of services, this could have serious implications particularly in relation to statutory services ultimately leading to service failure and/or reputational implications.

A significant factor that will affect this risk is Local Government Reorganisation [Risk C15]

Inherent risk level (no controls)

Probability: 4

Impact: 4

Risk score: 16 (amber)

Controls in place at MVDC

– Council Strategy 2024-28 approved to assist with prioritisation from April 2024, including development of Annual Plan and Business Plans

-Annual Plan 2026/27  agreed in light of  Local Government Reorganisation and resources required for transition planning during 2026/27

–  Up to date workforce data available to Strategic Leadership Team to enable effective management of workforce, inform business planning,  and the appraisal process

– Governance arrangements in place to provide organisational oversight, enabling re-prioritisation of  tasks and available resources where appropriate

– Effective arrangements in place regarding recruitment and retention which are kept under review. This includes feedback from applicants offered a job but did not accept and feedback from leavers.

– Controlled use of interim staff to cover business critical posts for short periods of time

-Making best use of internal staffing resources to free up capacity for those supporting the LGR transition process

– Annual review of cost of living increase award to ensure it is both affordable and reflective of additional pay inflation, including comparison with other authorities

Residual risk level (after existing controls)

Probability: 2

Impact: 4

Risk score: 8 (amber)

Movement of residual risk since last review

Down

Target risk level

Probability: 2

Impact: 4

Risk score: 8 (amber)

Risk owner – Member

SLT (Head of Paid service has delegated responsibility in the constitution for staffing matters)

Risk owner – Officer

Chief Executive

MVDC needs to ensure that all employees are aware of the organisation’s responsibilities in relation to safeguarding children and vulnerable adults.

This means being able to identify signs of concern and knowing when to share information and to report those. It also means ensuring that employees follow safe practice when delivering services. Due to the impact of ongoing economic uncertainty, more people continue to be vulnerable to changes in circumstances, financial or otherwise.

This risk is also informed by the impact of local government reorganisation.  The transition of Mole Valley’s safeguarding will be considered in light of the shift of functions into the East Surrey Council.

MVDC also needs to ensure that there is an appropriate response in place in the event of a Domestic Abuse Related Death Review or involvement in a Child Safeguarding Practice Review or a Safeguarding Adults Review.

Failure to fulfil our responsibilities in relation to identification of safeguarding risk could delay referrals for early intervention and lead to significant harm or death of a child or vulnerable adult and the potential ensuing legal action and reputational damage for the authority.

Inherent risk level (no controls)

Probability: 3

Impact: 4

Risk score: 12 (amber)

Controls in place at MVDC

– Policies and procedures for safeguarding in place and reviewed as appropriate

– On-line referral forms in place for children’s single point of access (CSPA) and via the SCC portal for multi-agency safeguarding hub (MASH) to track and follow up on concerns raised

– Procedures in place for Mole Valley Life services including Telecare and the Community Responder Service

– All employees undertake foundation level awareness training for safeguarding and new employees undertake this as part of their induction

– Enhanced level safeguarding training undertaken by relevant staff as identified according to their responsibilities

– Safeguarding forms part of the Terms of Reference of the Corporate Governance Board, including presentation of annual referral analysis

– Annual undertaking of S11 audit from Children’s Safeguarding Board, and involvement in Adult Safeguarding Board Quality Assurance activity

– Representation on the Surrey Adult Safeguarding Board, the Children’s Partnership Executive Group and the Safeguarding Lead officers Group

– Involvement in Surrey Lead Member and Lead Officer group chaired by SCC Cabinet lead Member

– Procedures in place for conducting Domestic Abuse Related Death Reviews, working with a central co-ordination team at Surrey County Council. Involvement in Domestic Abuse Related Death Oversight Group

– Safeguarding procedures in place in relation to the Homes for Ukraine scheme as set out in government guidance

Residual risk level (after existing controls)

Probability: 2

Impact: 2

Risk score: 4 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 2

Impact: 2

Risk score: 4 (green)

Risk owner – Member

Cabinet Member (Services and Security)

Risk owner – Officer

EHoS – Community

In declaring a Climate Emergency, MVDC has recognised the current environmental tipping point and is working towards being carbon neutral by 2030.  MVDC is committed to making a positive contribution at a local level through the implementation of the Climate Change Strategy for Mole Valley. The risk is that MVDC fails to deliver the Climate Change Strategy,  meaning that we do not to maximise achievement of carbon reduction and /or fail to maximise support to businesses and residents.

This risk is informed by the way we manage our workforce, estate and operations, coupled with competing priorities for financial resources, to assist in reducing our carbon footprint and make Mole Valley more resilient to the impacts of climate change.

The impact locally includes:

  • Increased likelihood of flooding impacting on properties
  • Extreme weather (heat and cold) impacting vulnerable residents and council assets
  • Extreme weather having a greater impact on the day to day delivery of services
  • Detrimental impact on the local environment

Inherent risk level (no controls)

Probability: 5

Impact: 3

Risk score: 15 (red)

Controls in place at MVDC

– Climate Change Strategy in place setting out the arrangements in place to reduce the impact of climate change at a local level

– Climate Change Adaptation Strategy in place to identify the impacts of climate change on Mole Valley and the Council’s long term strategy to adapt service delivery in response

– Carbon literacy training in place and being rolled out to inform how the workforce can make an impact through their job roles

-Carbon reduction commitment in business plans actively monitored

-Local Plan contains supportive policies for new developments and refurbishments

– Plans in place for flooding and snow/ice. Plans in development for prolonged red warnings for heat

– Sustainable Procurement Charter in place to ensure climate change sustainability of long-term contracts

-Information to support residents and business available in the Sustainable Mole Valley website

-Active seeking of funding opportunities

Residual risk level (after existing controls)

Probability: 3

Impact: 4

Risk score: 6 (amber)

Movement of residual risk since last review

Up

Target risk level

Probability: 3

Impact: 2

Risk score: 6 (green)

Risk owner – Member

Cabinet Member (Climate)

Risk owner – Officer

EHoS – Planning & Place

Proposed re-developments and regeneration schemes which are likely to result in asset disposals and capital receipts  fail to proceed. This could lead to capital receipts not being realised or receipt delayed. Where assets are identified for redevelopment, regeneration or disposal this could limit the Council’s ability to lease the assets because of the need to retain flexibilities to facilitate the the development scheme. Prolonged delays can lead to project viability challenges resulting in higher expenditure and lower capital receipts as well as unnecessary revenue and capital costs in relation to asset maintenance/management as a result of the delay.

This risk is informed by :

– Falls in capital values of assets due to market conditions

– Market conditions affecting project viability

– Planning and political risks as a result of potentially conflicting views from residents and other key stakeholders creating uncertainty

Please also see Risk C1d Reduction in capital value of and rental income from Investment Properties

Inherent risk level (no controls)

Probability: 3

Impact: 4

Risk score: 12 (amber)

Controls in place at MVDC

– Asset Management Strategy 2025-2030 in place

– Finance Team commission IFRS valuations from an independent valuer on a five year rolling programme

– Regular periodic reviews of business cases for property/project transactions

– Strategic Asset Management Working Group and Pippbrook Working Group in place to review and inform potential asset development and disposals

– Ensuring that recommendations put forward for approval at Cabinet are deliverable and/or that the risks are fully identified and explained with accompanying sensitivity analysis and independent advice received

-MVDC policy on non-statutory consultations and community engagement

– Due diligence undertaken on all potential transactions

– Forward planning and monitoring to enable MVDC to plan for worst case scenarios and plan the response

– Capacity to deliver assessed prior to commitment to delivery

-Development agreements in place for Swan Centre/Bull Hill and Claire House and James House

-Joint Venture set up with Kier with Joint Venture Board and appropriate governance arrangements and legal agreements

-Approval of the Planning Strategy Business Case and Annual Business Plan for the joint venture by Cabinet

-Consultation with residents

-Professional teams appointed to support developments

-Kier MVDC JV submitted planning application for TL scheme in Nov 2025

Residual risk level (after existing controls)

Probability: 2

Impact: 5

Risk score: 10 (amber)

Movement of residual risk since last review

None

Target risk level

Probability: 1

Impact: 5

Risk score: 5 (green)

Risk owner – Member

Cabinet Member (Commercial Assets and Projects)

Risk owner – Officer

EHoS – Resources

MVDC needs to make sure that arrangements are in place to ensure an effective response in an emergency situation.

As a Category one responder MVDC is required to comply with the duties set out in Civil Contingencies Act 2004.

If we fail to act effectively, this could lead to distress and harm, a loss of public trust, and a failure to provide civil protection to residents, businesses and the wider community.

This risk is informed by a number of issues, including:

  • Local or national level of emergency response required
  • The nature of the emergency, which could include for example power outage, flooding or other extreme weather conditions.

Inherent risk level (no controls)

Probability: 4

Impact: 5

Risk score: 20 (red)

Controls in place at MVDC

-Emergency Plans in place that comply with the duties of the Civil Contingencies Act 2004

-Emergency planning duty officer rota in place 365 days a year and regular training provided

-Named incident liaison officers

-Business Continuity Management MVDC Corporate Plan – Incident Management and Organisational Resource Plan in place that sets out key actions to be taken in response to an emergency

-All services have business continuity plans in place (on-going training re business resilience)

-Severe weather plan in place

-Multi-agency flood plan in place

-Emergency Assistance Centre Plan in place

-Winter preparedness plans in place

-Access to Resilience Direct Portal

-Lessons learnt from both local and major national incidents

-Active member of the Surrey Local Resilience Forum which publishes the Surrey Community Risk Register. This provides public information about the hazards that exist within the County and the control measures that are in place to mitigate their impact. The Register details the lead agency for each hazard identified. The responsibilities (specifically infrastructure/system failure and natural hazards) assigned to Mole Valley District Council are to be read in conjunction with this Strategic Risk Register.

Residual risk level (after existing controls)

Probability: 2

Impact: 3

Risk score: 6 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 2

Impact: 3

Risk score: 6 (green)

Risk owner – Member

Leader, Governance and Organisation

Risk owner – Officer

EHoS – People

Contract Management across the organisation is inconsistent. Despite corporate contract management guidance and some areas of good practice, we have found that contracts may not be consistently recorded on the Council’s contract register and that monitoring of expenditure against contracts and supplier performance by contract managers is inconsistent across the organisation.

This may result in:-

  • Lack of compliance with the Procurement Act 2023 and Transparency code reporting requirements
  • Poor services to residents due to contractor poor performance not being addressed
  • The Council being unaware of the risk of individual suppliers going into administration
  • Additional costs or loss of income to the Council
  • Incomplete or inaccurate information about contract arrangements passed to the new East Surrey Council

Inherent risk level (no controls)

Probability: 4

Impact: 3

Risk score: 12 (amber)

Controls in place at MVDC

-Contract management procedure rules in Constitution

-Contract Management Guidance Notes on the intranet

-Regular Contract Management Training in place

-Contracts Register in place and reviewed quarterly

-Monitoring of contract spend

-Regular financial health checks eg Dun and Bradstreet, undertaken on high and medium level contracts

-Internal Audit reviews

Residual risk level (after existing controls)

Probability: 3

Impact: 2

Risk score: 6 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 2

Impact: 2

Risk score: 4 (green)

Risk owner – Member

Cabinet Member (Finance)

Risk owner – Officer

EHoS – Resources

Waste collection and street cleaning are statutory duties under the Environmental Protection Act 1990, with the waste collection service being a service that is delivered to every household. Following a successful procurement, the four partner authorities, Mole Valley District Council, Elmbridge Borough Council, Surrey Heath Borough Council and Woking Borough Council, approved the award of contract to Veolia, and that decision was also approved by both East and West Surrey Shadow Authorities in July 2026.  The contract with Veolia and the underpinning inter authority agreements were signed in August 2026, which provides ten months to manage the mobilisation of the contract by Veolia and the demobilisation of the contract by Amey at the same time as overseeing business as usual service delivery to residents up to and beyond vesting day in both East and West Surrey.  The new contract will commence on 6 June 2027 and at the same time in all four areas. The risk is around effective mobilisation as the old contract ends and the new one begins at a time of significant change as a result of Local Government Reorganisation.

 

This risk is informed by:

  • The new contract is going live just two months after vesting day.
  • Mobilisation requires input from a range of authority teams outside Joint Waste Solutions, including Asset Management, Customer Services, Communications, Finance and ICT, at a time when preparation for vesting day will also require resources and create some uncertainties and/or dependencies (bank accounts, VAT numbers, insurance arrangements, confirmation of principal place of business) so that Veolia can set up the authorities as a new client.  The senior officer team is yet to be appointed and engagement with them, the relevant responsible officers (as and when appointed) and ensuring retention of critical service knowledge are all seen as key to that transition process.
  • In common with Elmbridge, but in contrast to Surrey Heath and Woking, Mole Valley retains responsibility for customer services.  The successful integration of Veolia’s IT solution with Mole Valley’s customer service platform is critical.  There is an opportunity for Elmbridge and Mole Valley to work on some aspects of this as ‘one team’ as a way of making best use of resources in relation to IT as both authorities have implemented Granicus although there are likely to be local differences.
  • There will be changes to the service shortly after vesting day and ensuring ongoing up to date resident communications are maintained before and after vesting day will be key (e.g the introduction of a new bookable free textile and WEE service forms part of the service solution).
  • The MVDC Property Team will need to progress any works required at the Depot in consultation with Amey and the new provider.
  • Pause on strategic asset decisions relating to the depot available to support the waste collection and street cleaning service/service provider is a potential constraint on the ability to implement some of the proposals to decarbonise the fleet (such as HVO and or electric charging capabilties) as it affects the ability to develop an outline business case given the uncertainty over the potential payback period.
  • Uncertainty from central government in terms of future strategic waste plans and related targets – examples include decisions to defer the household kerbside collection of flexible plastics to 2030, the current lack of reprocessor capacity to accept materials such as fridge freezers, tetrapak and flexible plastics, delays to the implementation of Deposit Return Scheme to Oct 2027.
  • MVDC offers a garden waste service to its residents which generates revenue for the authority as well as contributes to our recycling rates. The new authority will need to decide the fees and charges that it wishes to apply to the garden waste service (taking account of the cost recovery principle and the updated pricing model that applies to the new contract) and changes to other costs in the Veolia pricing schedule will need to be reviewed and flowed through into updated fees and charges to ensure cost recovery, unless East Surrey wishes to phase any above inflation impact on residents through some form of subsidy.
  • Uncertainty as to the impact of disaggregation of Surrey County Council as the Waste Disposal Authority on waste infrastructure, key contacts and waste data flows.
  • The actual cost of the service in year 1 has been modelled but there will be various true-ups/adjustments to the year 1 cost, relating to inflation, decisions around fuel and TUPE corrections.

Inherent risk level (no controls)

Probability: 5

Impact: 5

Risk score: 25 (red)

Controls in place at MVDC

-New contract for waste collections in Mole Valley (Surrey Heath, Elmbridge and Woking) signed in September 2026. Veolia will take over in June 2027.

-Inter-Authority Agreement agreed by MVDC and East and West Surrey Council Shadow Executives

-Building in flexibility to future arrangements

-Joint Waste Solutions (JWS) project managing the reprocurement and the various workstreams

-The capital programme for 2026/27 is adequate to fund the renewal of fleet vehicles and works to the Depot

-The future of the Material Recycling Facility (MRF) is part of a recommendation to repurpose the site as a dry mixed recycling waste transfer station which was approved by MVDC Cabinet in June and by East Surrey Shadow Executive in July 26. The facility is due to be handed over to SCC in November 2026 and will be managed through their contract with Suez. This option has the support of JWS and SCC but remains subject to successful negotiations with Grundons

-S151 officers attends regular cross council and partnership meetings to be assured that financial implications are built into the future budget setting processes for East and West Surrey Councils

-Regular member briefings incorporated into the procurement project plan

-Making use of expertise and capacity in Joint Waste Solutions (JWS) to undertake horizon scanning

-Commercial disputes with the current service provider have been resolved

-In relation to Local Government Reorganisation a Joint Implementation Team has been established with waste falling under the Place theme

Residual risk level (after existing controls)

Probability: 2

Impact: 4

Risk score: 8 (amber)

Movement of residual risk since last review

Down

Target risk level

Probability: 2

Impact: 3

Risk score: 6 (green)

Risk owner – Member

Cabinet Member (Waste, Recycling and Environmental Health)

Risk owner – Officer

EHoS – Commercial

Central government has confirmed the implementation of Local Government Reorganisation in Surrey.  Elections to the new shadow unitary councils were held in May 2026. The new unitaries will go live on 1 April 2027 (vesting day).

The Structural Changes Order is now in effect. Section 16 requires co-operation between authorities in order to secure the economic, effective and efficient and timely transfer of functions, assets, rights and liabilities.

MVDC will continue to exist until 31 March 2027.  During this time the council needs to continue provide essential services, achieve its corporate objectives and deliver against strategies and plans. There is added complexity in terms of governance in making key decisions as some of these are subject to consultation with the new shadow authority.

There is risk that, if MVDC did not have mitigations in place some functions may not be safe and legal at the point of vesting day.

Risk C7, Organisational Capacity to Deliver identifies that there is risk that during this transition phase MVDC may have reduced staffing capacity as a result of staff leaving MVDC and/ or working for or in support of the shadow authority.

Inherent risk level (no controls)

Probability: 5

Impact: 4

Risk score: 20 (red)

Controls in place at MVDC

-Active engagement with MHCLG and with the Implementation Team to make sure we understand and contribute to the process

-Active participation in the Implementation Team Themes and workstreams and actioning any requests for information in a timely and accurate way

-Subject Matter Experts allocated to each workstream to ensure two way communication and identification of any actions for MVDC

-Communications with Members, residents, business and key stakeholders / partners via the Implementation Team

-Ensure that strategies and plans remain deliverable and appropriate within existing resources

Residual risk level (after existing controls)

Probability: 2

Impact: 3

Risk score: 6 (green)

Movement of residual risk since last review

Down

Target risk level

Probability: 2

Impact: 3

Risk score: 6 (green)

Risk owner – Member

Leader, Governance and Organisation

Risk owner – Officer

Chief Executive

Risk of exceeding the VAT partial exemption limit could lead to additional cost for the Council in 2026/27 as we would no longer be able to reclaim VAT on expenditure on exempt services and activities.

This risk informed by MVDCs annual calculation of its partial exemption position which has shown that the Council is close to its limit.

Inherent risk level (no controls)

Probability: 5

Impact: 4

Risk score: 20 (red)

Controls in place at MVDC

-Regular monitoring of VAT partial exemption position as part of regular Business and Budget monitoring reports to Scrutiny and Cabinet

-Monthly VAT returns to HMRC

-Annual internal partial exemption calculation

-Training provided to staff on VAT

-Access to VAT specialist advisors

-Members of the Finance Team provide advice and support to Business Managers on VAT

-Advice to services provided to limit number of partially exempt services and activities the Council is providing during 2026/27

Residual risk level (after existing controls)

Probability: 2

Impact: 3

Risk score: 6 (green)

Movement of residual risk since last review

None

Target risk level

Probability: 1

Impact: 1

Risk score: 1 (green)

Risk owner – Member

Cabinet Member (Finance)

Risk owner – Officer

EHoS – Resources

Key: EHoS = Executive Head of Service.

Additions / deletions in last 12 months:-

Additions:

  • January 2026 – C16 Exceeding VAT partial exemption limit

Deletions:

  • July 2025 – C4b IT (Operational Resilience)